KSBT 实际/计划 作业价格

  • 001:
  • The price of the activity type is determined automatically based on theplanned activity and the planned costs required for this plan activityquantity.
  • Fixed price: Fixed planned costs/plan activity quantity
  • Variable price: Variable planned costs/plan activity quantity
  • Total price: Fixed price + variable price

 

  • 005: (actual price)
  • The R/3 System determines the price of the activity type using theactual activity of the cost center.

 